Tarana Foundation in collaboration the German Embassy of Colombo and the support of relevant Officials have successfully concluded WASH (Water, Sanitation and Hygiene) Projects in Dehiattakandiya, Jaffna, Anuradhapura and Padiyatalawa for the year 2020.
We are grateful to the German Embassy for funding this MICRO project and for partnering and placing confidence in our ability to see this project through within the targeted timelines.
We also sincerely thank all who partnered with us to make this a reality to bring clean water and sanitation facilities to rural areas in Sri Lanka.
Dehiattakandiya | |||||
Bakmeedeniya Maha Vidyalaya | Construct a filtering system | 230,000.00 | |||
Kadirapura Primary Vidyalaya | Construct a water system | 59,580.00 | |||
Kelegama Vidyalaya | Construct a water system | 85,255.00 | |||
Lathpandura Primary Vidyalaya | Construct a water system | 91,755.00 | |||
Medagama Maha Vidyalaya | Construct a water tank to store water | 99,300.00 | |||
Muwapetigewela Vidyalaya | Construct a water tank to store water | 254,725.00 | |||
Nagaswewa Vidyalaya | Construct a water tank to store water and also fix a motor to the well to pump the water | 60,000.00 | |||
Paranagama Vidyalaya | Construct a water tank to store water from the well | 112,000.00 | |||
Salpitigama Vidyalaya | Construct a water tank to store water | 100,100.00 | |||
Sooriyapokuna Maha Vidyalaya | Construct a tube well | 229,200.00 | |||
Uttalapura Primary Vidyalaya | Construct a water tank to store water. | 99,850.00 | |||
Webadagama Vidyalaya | Construct a water tank to store water | 230,490.00 | |||
Samanalathenna Primary School | Construct a water system | 20,615.00 | |||
Jaffna | |||||
Subramania Vidyalayam, Delft | Supply drinking water to the school | 150,000.00 | |||
Kayts Roman Catholic Boys School | Renovate to enable adequate sanitary facilities | 150,000.00 | |||
Anuradhapura | |||||
Thambiyawa Dharmapala, Thanthrimale | Construct a water storage system to store adequate water | 197,275.00 | |||
Padiyatalawa | |||||
Sri Sunethraramaya, Padiyatalawa | Construction of a tube well | 180,000.00 | |||
Technical Officer (Transport cost & any other expenses) | 60,000.00 |